Park Ave Bridge Update – December 2022

Park Ave Pier 2

Park Avenue South Abutment and Piers 1 & 2 have been constructed and concrete beams for Spans 1 & 2 have been installed. Currently approximately 60% of the existing bridge has been removed with demolition beginning on the north side. The causeway has been relocated to the north side of the river to allow construction operations to continue with the remaining Piers 3 & 4. It is anticipated that the bridge may be complete Fall 2023.