11th Street Bridge Update – December 2022
![(1)_11th Street causeway and removals near center river looking at Phase 2 11th street causeway](http://waterloobridgesproject.com/wp-content/uploads/2023/02/1_11th-Street-causeway-and-removals-near-center-river-looking-at-Phase-2-578x246.jpg)
11th Street north side half of the existing bridge has been removed, including old Piers 3 & 4. Contractor has driven steel piles and has started placing the north abutment concrete. Current construction operations are focused on installing concrete drilled shaft foundations for new Piers 3 & 4 during the winter months. Anticipated completion of the bridge may be spring 2024 depending on weather and river conditions.