11th Street Bridge Update – December 2022

11th street causeway

11th Street north side half of the existing bridge has been removed, including old Piers 3 & 4. Contractor has driven steel piles and has started placing the north abutment concrete. Current construction operations are focused on installing concrete drilled shaft foundations for new Piers 3 & 4 during the winter months. Anticipated completion of the bridge may be spring 2024 depending on weather and river conditions.